Installation
In order to obtain a radiant system with the maximum perfor-
mance, after taking the preliminary precautions listed above, it
is necessary to follow this procedure:
•
Install the expansion edge strip;
•
Install the panel, starting from the side walls and connecting
one panel to the other using the side fastening system
provided (bonding the upper sheets, interlocking of the
perimeter grooves, interlocking the male/female perimeter
bosses;
•
Install the pipe on the panel realising the circuits as per the
installation diagram;
•
Ensure that the panel is in contact with the sub-floor and
secure it in the case of lifting;
•
Perform the leak test;
•
Evaluate and position the expansion joint strips according
to the UNI 1264 standard and/or according to the screed
manufacturer's instructions;
•
Proceed to pour the screed to a suitable thickness above
the pipe. For sand and cement screeds, respect the proper
water/cement ratio of 0.55;
•
Carry out screed heating tests as per UNI 1264 and/or as
indicated by the screed supplier. In particular:
•
At least 21 days after the laying of sand and cement
screeds;
•
At least 7 days after the laying of calcium sulphate-
based screeds;
•
Maintain at 20 to 25 °C for at least 3 days, and then
raise to the maximum design temperature, to be
maintained for at least 4 days;
•
Install the floor covering.